Ten thousand staples! Oh man, I think that Jeanette and I are going to be
seeing staples in our dreams for the next week since we removed so many of
them from the bridge wood yesterday, working with Mike and Ben on the first
stage of preparatory work on the Laurel Gulch project.
Wayne and Tom joined the effort to collect cut-up tree segments along the
hillsides further up on the canyon so that they can be sold a fire wood,
joining a number of other volunteers from other groups who work in the
canyons, and since I thought that they had enough volunteers for that
project, I stayed below at the Rincon Fire Station to lend a hand with
the wood that will be assembled to create the new bridge.
And what fun it was, too! Three large bundles of previously cut and
drilled wood was waiting to be unpacked, covered in plastic sheeting that
had been stapled to the wood. And then stapled again. And then once
again. And then stapled one more time for good measure!
Who ever packaged up the bridge parts must have wanted to be absolutely
sure that the plastic covering didn't shift a micrometer since we must
have spent four or five hours removing staples, usually digging in to the
wood with screw drivers tapped in to place with a hammer and a hatchet,
and yanking them out with pliers.
Much of the wood was literally dripping with Copper Naphthenate, the
biochemically safe wood preservative treatment that should keep all of
the wood parts healthy for at least the next century or there about.
(See
http://www.merichem.com/news/news2.php for details about how wood
is -- excuse the vulgarity, please! -- "thermally butt
treated!" with the chemical.)
The wood parts were plucked off of the shipping stacks and set upon wood
runners so that they could dry for the next two weeks while the staple
removal continued as each piece was inspected and added to the drying-out
stacks.
Calculations were performed to determine the weight of some of the parts,
and then got re-computed after we decided that sixteen million pounds was
probably not correct. We laid down on the concrete with paper and pen and
worked out the weight of the main beams a second time and got closer to
what we thought was a reasonable answer -- fifty six thousand pounds which,
while probably still not right was at least an order of magnitude more
correct.
Since some of us just remove staples and don't do math, we left the mental
calculations to Mike and Ben to perform. When Mike suggested that the
square root of negative one should be included in the figuring of the
beam's weight, us staple removers decided it had been wise not to get
involved.
Mike and Ben figured out the various measurements and spacing of the tread
pieces that would need to be laid out and drilled after the wood is given
some time to dry. Of the four of us, I think Mike probably has a better
understanding of geometry, and since my brain doesn't work that way, I
couldn't even visualize how the wood parts was going to form something
resembling a bridge, leave alone figure out where to hammer in a nail --
so staple removing was a good job for me.
Tom came down to the Fire Station after the wood gathering effort ended
early due to the need to always consider fire hazards, and he joined the
team of engineers making sure that all the parts were accounted for, all
the measurements were correct, and all the hardware was of the right
caliber for the various weights and tensions that bridge transport and
assembly required.
Aside from prep on the wood, there was also many bags of "sacrete"
that needed to be moved from storage and get placed on the concrete staging
apron. I offered to assist in that but when I was informed that each bag
weighed 90 pounds, I recalled my offer. Mike asked six of the Engine 22
Fire Fighter men and women crew to come move the bags and they got it done
quickly and, annoying, easily. Ah, to be young again!
The proposed project schedule will be
posted elsewhere on
this web site in a section specifically dedicated to the project however
the schedule so far is thus:
November 2 -- Rincon Fire Station. The two main beams of the bridge
will be laid out and about 16 of the treads will be assembled along with
strengthening supports so that the partially assembled bridge can be air
lifted by helicopter to the gulch.
November 8 and 9 -- Rincon Fire Station. Package up the partially
assembled bridge and as much of the heavy materials and equipment that
can be carried by helicopter as possible, reconfirming that everything
has been assembled and is ready to be transported, either by air or by
horse back.
November 15 and 16 -- Rincon Fire Station and Laurel Gulch. Air
transport of sacrete and other materials to the Laurel Gulch work site,
building the bridge footings, and getting ready to receive the partially
assembled bridge. Yep, that's an over night bundle of fun!
November 22 and 23 -- Rincon Fire Station and Laurel Gulch. Air
transport of partially assembled bridge to the point where the bridge
itself is in place and people may walk across it. Not all of the work
needs to be completed, just enough so that the usage of the bridge is
safe. That's also an over night project, and if there is any time
available, the old bridge will be disassembled so that it can be hauled
out on our backs.
November 29 and 30 -- Laurel Gulch. Thanksgiving Day week end
however we will probably be able to get volunteers anyway. The remaining
work on the bridge will probably be installing the hand rails and anything
else that needs to be done.
As you can see, it's a full schedule and as many volunteers as we can get
will be needed.
You may leave a comment about this page which everyone else will be able to read:
Two of the packaged bridge parts before they are taken apart and inspected
The other two packages get taken apart and moved off to dry
The primary drying stack, many staples get removed
Other work taking place at the Rincon Fire Station
Counting the parts and taking inventory
The staple removal job took a log time
The other two stacks get taken apart and set aside to dry
Not related: We get a rope pulling gasoline power to donated to us!
Not related: I can't wait to fire this puppy and pull something with it
Jeanette takes a break under the available shade
Not related: Fake grave site at the Environmental Education Center at Rincon
Not related: Taking a look at the last bridge that we completed
Not related: The last bridge we did looks great!
A final look at the main bridge beams that still need to dry. Heavy!
This web site is not operated or maintained by the US Forest Service, and
the USFS does not have any responsibility for the contents of any page
provided on the http://CrystalLake.Name/ web site. Also this web site is
not connected in any way with any of the volunteer organizations that are
mentioned in various web pages, including the
San Gabriel Mountains
Trailbuilders (SGMTBs) or the
Angeles Volunteers Association
(AVA.) This web site is privately owned and operated.
Please note that information on this web page may be inaccurate.