Today the San Gabriel Mountains
Trailbuilders continued work
on the Winnona Trail within the
Crystal
Lake Recreation Area which starts at the lake's parking lot, winds its
way up to Islip
Ridge and eventually gives hiking access to various places such as
Windy Gap and
Angeles Crest
Highway as well as a number of other trails.
And what fun it was, too! This would be the last day of working to remove
the dead trees down across the hiking trail for the Summer since the
Trailbuilder schedule shows other obligations for the immediate future
which lead well in to the expected season of snow,.so one last drive to
buck up as many
downed trees as we could was made today while further below Trailbuilders
also worked to restore the trail, removing
Yerba
Santa from the trail, cutting back or removing brush, and generally
working the tread on the trail.
It was a good day for the effort since the day was cool and though we were
above the heavy cloud layer smothering the cities below, the temperatures
were cool enough so that we didn't run out of water this time. Ha!
We met at the
The big tool box we keep at Rincon had been relocated and the equipment
inside had been shifted around and generally shook up only a little bit
so we were able to straighten some things up, go collect the safety fuel
lock-box that had not made the move, get our
Kevlar
safety chaps and helmets, bright safety vests (because poachers and
other drunks with firearms need a visible target to shoot at) and
eventually we continued on up the mountain to Crystal Lake.
Today's safety rundown was quick and brief since all of today's volunteers
were long-time Trailbuilders. Mike #1 was back for the day after spending
over a year volunteering further up North, and Mike #2 was with us, as was
Bron, Ben, Jeanette, Vincent, Christopher, Bryan, and myself. Since today's
Project
Activity Level (PDF file) indicated that we could work until 13:00
with the gasoline powered saws before we must stop using them. (We also
routinely examine the general Job Hazard Analysis which volunteers working
within this regime often work within, an example of which
can
be found here (PDF file).)
I used our safety radio to call in to our
Angeles
Dispatch Overlords who provide radio safety oversight for volunteers,
allowing contact with fire fighters, medical rescue, law enforcement, and
Forest Service management, letting
Dispatch know where we would be and how many of us would be working on
the trail.
The last day of effort we had lightening strikes along
Mount Waterman and points North
which were walking generally South toward us and dumping a lot of water in
the region to the point where a
flash flood alert
was issued by Dispatch. (Staying informed by radio is a major safety aspect
of volunteer work.)
We split up along the trail. The sawing teams would need to hike up about 3
miles.
We had three qualified and certified
sawers today, Mike #1,
Bryan, and myself, and we had three saws, one of them a 12-inch, very light
saw that was expected to be used to remove limbs. Each sawyer, however, is
required to have a swamper assigned to him or her and since the forward
team consisted of Mike, Christopher, Bryan and myself, we could only operate
two of the saws.
We hiked up to where we had stopped bucking on the previous day's effort,
passing three obstructions along the way that were newly fallen and will
need to be removed, eventually. At the first work site we examined the
chainsaws and started working on getting them running for the day.
The best-laid plans of mice, as the saying goes... The 12-inch saw's
pull-cord handle broke so Bryan had to crack open the saw and fix that.
Mike's saw started right up however the third saw took a fair amount of
time to get running. Within the first hour of effort, the 12-inch saw's
pull-cord snapped and that was the end of that saw's usefulness for the
day since new pull-cords are not part of our usual repair packs.
Mike and I formed one team with Mike sawing and I swamping. Christopher
and Bryan formed the other team with Bryan sawing and Christopher swamping.
Both teams had a large medical kit, shovel, fire extinguisher, Kevlar
safety chaps, helmets, ear protectors, face guards, fuel, and oil.
The first downed tree was a difficult one, consisting of numerous limbs
on a tree about 60 feet long which was laying directly along the trail,
and Mike and I worked on that obstruction while the other team headed up
the ridge to the next blockage.
While limbing the tree we noticed that the saw was "four stroking,"
Bryan called it, it was not running correctly in that at high speed the saw's
noise had a staccato
briiipppp! to it and usually the saws operate without much visible smoke
however today we had more smoke than expected.
Regardless, work continued until the tree could be bucked and then shoved
off the trail by laying on our backs and shoving with our feet. After
cleaning off the trail we packed things up and continued on up the trail.
The other team had managed to clear a very large jumble
jack straws
pile of trunks, limbs, bark, and brush which I had expected would need
half a day to clear but they had managed to remove after about an hour.
13:00 O’clock came too quickly and while we managed to get some major
blockages removed, we did not make it to the point where the trail meets
the Islip junction, nor did we manage to get to where the trail is
obscured enough to warrant flagging the trail.
Then came the need to collect all of the tools strung out along the half
mile or so below us. Three chainsaws, two repair kits, lots of bottles of
fuel and oil, two medical kits, chaps, helmets, ear protectors, face guards,
wedges, shovels, three
McLeods an ax,
a pickaxe, a heavy rock bar, and various other tools had to be carried down
in addition to whatever personal equipment we had (radios, water, and such.)
On the way down we passed Vincent and Mike #2, and because we were pretty
heavily loaded down with tools and equipment, they lent a hand, and Mike
carried the heaviest saw down the rest of the way -- which was good because
I was pretty exhausted by then.
Also along the way we got to see how much of the trail had been
re-established and re-worked by the rest of the volunteers today, with large
sections of that sharp bush I think is called "Buck Thorn" having
been removed in places where hikers had to go around it.
Around 15:30 or so we assembled in the parking lot at the trailhead and took
stock of where we were, sorting through the tools and getting an idea of
what we might have left up there that will need to be retrieved after the
snows melt.
We packed up and headed back down to Rincon where we dropped off our tools
and equipment, informed Angeles Dispatch that we were done for the day, and
then we were done!
The next volunteer day is 30/October/2010 and it is expected that we might
work along
Upper Bear
Creek Trail with a number of
Boy Scouts to see what
the condition of the trail is and to make sure that the trail is reasonably
safe and useable.
Ben White gives the morning's safety run-down at the trailhead
Christopher gets safety equipment in place
Bryan with the 12-inch chainsaw
Mike with his safety equipment
At the first downed tree effort of the day Mike reports on in the radio
After a considerable amount of limbing on the first downed tree we see progress
Half of the first tree has been bucked up and removed
The first project has been completely delimbed and the larger bucking starts
The first major obstruction has been cleared
A set of hazard trees are carefully bucked and removed from the trail
We pause to take stock of the first hazard tree after removal
Mike and christopher examine the lay of the next downed tree
Bryan gets safety helmet in place before the next bucking
After 13:00 we start heading back down the mountain
Mike at the end of the day complete with fire-resistant clothes
This web site is not operated or maintained by the US Forest Service, and
the USFS does not have any responsibility for the contents of any page
provided on the http://CrystalLake.Name/ web site. Also this web site is
not connected in any way with any of the volunteer organizations that are
mentioned in various web pages, including the
San Gabriel Mountains
Trailbuilders (SGMTBs) or the
Angeles Volunteers Association
(AVA.) This web site is privately owned and operated.
Please note that information on this web page may be inaccurate.